Tasks will always honor their constraint dates
Specifies that Project schedules tasks according to their constraint dates.
If you enable this setting, task constraints will always be honored when tasks are scheduled.
If you disable or do not configure this setting, the user's default setting is used.
Registry Information
| Vendor | Microsoft |
|---|---|
| Product | Microsoft Project 2016 |
| Category | Microsoft Project 2016 › Project Options › Schedule › Scheduling options for 'Project1' |
| Applies to | User Configuration |
| Supported on | Windows7 |
| Registry Key | [HKCU]softwarepoliciesmicrosoftoffice16.0ms projectoptionsscheduling |
| Value Name | honorconstraints |
| Type | REG_DWORD |
| Enabled value | 1 |
| Disabled value | 0 |
Registry File (.reg)
Windows Registry Editor Version 5.00
; Enable the policy
[HKEY_CURRENT_USERsoftwarepoliciesmicrosoftoffice16.0ms projectoptionsscheduling]
"honorconstraints"=dword:00000001
; Disable the policy
[HKEY_CURRENT_USERsoftwarepoliciesmicrosoftoffice16.0ms projectoptionsscheduling]
"honorconstraints"=dword:00000000PowerShell
# Enable the policy
Set-ItemProperty -Path "HKCU:softwarepoliciesmicrosoftoffice16.0ms projectoptionsscheduling" -Name "honorconstraints" -Value 1 -Type DWord
# Disable the policy
Set-ItemProperty -Path "HKCU:softwarepoliciesmicrosoftoffice16.0ms projectoptionsscheduling" -Name "honorconstraints" -Value 0 -Type DWord